Central Ranges Gas Pipeline Pty Ltd proposes to build a natural gas reticulation system in the Central Ranges district of NSW. The Tribunal is reviewing CRP's proposed access arrangement to apply from 2006 until 2019.
Central Ranges Gas Pipeline Pty Ltd proposes to build a natural gas reticulation system in the Central Ranges district of NSW. The Tribunal is reviewing CRP's proposed access arrangement to apply from 2006 until 2019.
The Tribunal approved the revised access arrangement submitted by Central Ranges Pipeline Gas Networks in November 2005.
Final Decision approving Central Ranges Pipeline Gas Network's revised access arrangement and access arrangement information (submitted 18 November 2005) and final report setting out the Tribunal's
Revised access arrangement amended in response to the Tribunal's draft decision released in October 2005.
Australian Competition and Consumer Commission (ACCC) and IPART issues draft decisions on access arrangement submitted by Central Ranges Pipeline
Sets out Tribunals draft decision on CRP's proposed access arrangement for the period 2006 to 2009/10.
The Tribunal seeks submissions on CRP’s proposed access arrangement by 26 September 2005. The manner in which submissions should be made is set out in this advertisement.
Proposed access arrangement relating to the proposed natural gas distribution network in the Central Ranges district of NSW.
Proposed access arrangement information relating to the proposed natural gas distribution network in the Central Ranges district of NSW.
Explains Tribunal’s decision on the Central Ranges Natural Gas and Telecommunications Association Incorporated’s final approval request for the outcome of its tender process to select an organisati